A CCM migration has three cost components, one for each stage of the project:
- Investigation: finding out what the old platform actually does, and choosing the route.
- Implementation: rebuilding templates, business rules, channels and integrations on the new platform, and testing them.
- Running: the platform after go-live, including the licence or service fee.
The estimate that reaches the board usually holds a licence and a conversion quote. Investigation is often missing, and running costs are left to a later budget. Those two lines decide whether the project lands on budget.
What are the cost components of a CCM migration?
| Component | What is done | How it is usually priced |
|---|---|---|
| Investigation | Inventory of templates, business rules, channels, integrations and owners; choice of route | Estimated hours times an hourly rate, often as a separate first phase |
| Implementation | Templates and logic rebuilt on the new platform, output tested, sign-off per document family | Estimated hours times an hourly rate |
| Running | Platform, hosting, upgrades, support and archive after go-live | A licence plus your own team, or a primarily volume-based fee |
What happens in the investigation stage?
The investigation writes down what the old platform does: every template still in use, every channel, every integration with a source system or a print provider, every business rule buried in template logic, and the business owner who signs off each document family.
Most organisations assume this list exists. What exists is usually a folder of templates and a few people who remember why a particular clause goes to a particular customer group. Skipping the investigation does not save the work. It moves it into implementation, where it is more expensive and comes later.
The stage ends with a choice of route: upgrade with the current vendor, migrate to another platform, or move to a managed service. That choice sets the cost of the other two stages.
How is implementation priced?
Implementation is usually quoted as an estimate of hours times an hourly rate. The hours depend less on the number of templates than on the logic inside them: which variant is sent when, which clauses are mandatory for which product, which data field drives which paragraph. A letter with thirty conditional branches takes many times longer to rebuild than a letter with none, and both count as one template.
Two things keep the estimate honest:
- Retire before you convert. A template nobody has produced in a year does not move, and does not get paid for. This is where experience pays off: a CCM partner that has done this before knows which templates can go, which can be merged, and where the logic is hiding, and reaches that shortlist in less time than an internal team working from the folder.
- Agree what the estimate covers before you accept it. It should include the business rules and the comparison of old against new output on real data. Anything that is not in the estimate is added later, at the end of the project, when there is no room left to say no.
How are running costs priced?
Running costs usually follow one of three models:
- Licence model. A licence or subscription for the platform, plus your own team to run it, the infrastructure, the upgrades and the archive. Each of these is a separate line, and most of them sit outside the project budget.
- Buying the software. A one-off purchase of a perpetual licence, with a yearly maintenance fee on top and the same team, infrastructure and upgrades as the licence model. This used to be the norm and is now rare, as vendors have moved to subscriptions.
- Volume-based managed service. A primarily volume-based fee, set by the number of communications you send, covering the platform, hosting, upgrades and support. Eclipse prices its managed service this way, so the cost moves with what you actually produce.
| Upgrade with the current vendor | Migrate to another platform | Managed service | |
|---|---|---|---|
| Pricing basis | Licence plus your own team | Licence plus your own team | A primarily volume-based fee |
| Platform team | Retained | Retained, retrained | Not needed; the provider runs it |
| Upgrades and patching | Yours | Yours | Usually included in the fee |
Whichever model you choose, the old platform keeps costing money until it is switched off. Put its decommission date in the plan and in the budget.
How to build an estimate that holds
- Get the support end date or contract end date in writing.
- Fund the investigation as its own stage, before anyone quotes implementation.
- Retire unused templates and merge variants before counting what moves.
- Agree what the implementation estimate covers, including business rules and testing, before you accept it.
- Add the running cost of the first two years for each route, including the old platform until it is switched off.
Then compare the routes on the total of all three components, not on the licence.
Frequently asked questions
How much does a CCM migration cost?
There is no useful single figure. The total depends on the number of document families, the business rules inside them, the channels and integrations involved, and the running model you choose. A complete estimate covers investigation, implementation and running.
What is the biggest hidden cost in a CCM migration?
Business rules that nobody documented. They are invisible in a template count and surface late, when they are rebuilt under time pressure. A proper investigation is the cheapest way to find them.
Is a managed CCM service cheaper than running the platform yourself?
That depends on your volume and on the team you would otherwise keep. A primarily volume-based fee makes the cost easy to forecast and replaces a staffing problem with a contracted service.
How long does the old platform keep costing money?
Until it is decommissioned. Put a decommission date in the plan and in the budget.
Related: Understanding the cost and value of CCM solutions and CCM, CRM and marketing automation: who does what?.
If you are putting a migration estimate in front of a board this quarter, this is the breakdown we walk through most weeks. Happy to go through yours.